Category Archives: success_story

TP8 – Mitigation plant

In IWTP8, a Mitigation plant was implemented in 2015 based on a MaSa Design to increase the treatment capacity by 20,000 m3/day. This Mitigation plant is an additional treatment for stage 1 with nine Dissolved Air Floated Unit (DAF) and 3 centrifuges to remove the total suspended solids from the flow....

Yanbu II and Sanitary Plant

Commissioning of new unit Supply Potable Water Capacity of 60,000 m3/day Process water 40,000 m3/day + Potable water 20,000 m3/day = Total 60,000 m3/day for the 2 units, only export pumps. Sanitary Water Treatment Plant 2 Capacity of 47,000 m3/day...

CPO

Integrated system New technology Reliability team CPO (GIS – Modernization) CPO GIS digitization of Potable Water, Reclaimed Water and Sea Water Facility are 100% completed. GIS digitized data field survey verification is on-going with 55% completion, planned for completion in 2016....

[getAllPostsNews]

×